Excavation & Trenching Safety Toolbox Talk
Today's Topic
Excavation & Trenching safety highlights:
A cubic yard of soil weighs approximately 3,000 lbs.
Cave-ins can kill instantly.
Call Before You Dig
Call 811 every time, no exceptions.
Hand-dig within the tolerance zone.
Know where all utilities are before breaking ground.
Protective Systems
Required at 5 ft depth: sloping, benching, shoring, or a trench box.
Soil type determines the protective system required.
A competent person decides the appropriate measures.
Egress & Spoil Piles
Ladder or ramp within 25 ft of every worker in a trench 4+ ft deep.
Spoil pile must be a minimum of 2 ft from the edge.
Today's Discussion Questions
Do we have a competent person assigned to today's excavation?
Has 811 been called for this dig?